What stage payments are, and when to use them
Stage payments split the price of a job into parts paid as it goes: some before you start, some at set points along the way, and the rest when it's done. On a two-day job they're not worth the paperwork. On an extension, a loft, a kitchen or a rewire that runs for weeks, they're the difference between the job paying for itself and you carrying it on your card.
They protect the customer too. They pay for work they can see has been done, rather than handing over a large sum up front, and you both find out early if something isn't right.
How to set the stages
Good stages are easy to agree and impossible to argue about. A few rules make them so.
- A deposit first, before you order anything, sized to cover the materials you're buying up front.
- Tie each stage to something both of you can see is finished: 'foundations in', 'roof watertight', 'first fix complete', 'units fitted'. Not 'week three', which moves if week three slips.
- Keep each payment roughly in step with what you've spent and done by then, so you're never far ahead of the money.
- Leave a real final payment for completion, big enough that finishing matters to both of you, but not so big it's most of your profit.
- Only include a retention, money held back until after a defects period, if the contract really has one, and write down the release date. On domestic work it's unusual, so don't offer one by habit.
Writing stage payments into the quote
The stages belong on the quote, as a schedule: what each stage is, how much it is, and when it's due once reached. When the customer accepts the quote, they're accepting the schedule with it. Agreeing stages on the drive and never writing them down is how 'I thought I paid at the end' starts.
Add one line on what happens if a payment is late. For a householder, your quote is the only rulebook there is, so this is the line that lets you stop work fairly if you ever need to. The example below uses made-up figures.
Example only: garage conversion, total £24,000.00. Stage 1, deposit on acceptance, before materials are ordered: £4,800.00 (20%). Stage 2, when the walls are built and the window and door are fitted: £7,200.00 (30%). Stage 3, when first fix is complete and the walls are plastered: £7,200.00 (30%). Stage 4, on completion: £4,800.00 (20%). Each stage is invoiced when it's reached and is due within 7 days of the invoice. If a stage payment is more than 7 days late, I may pause work after giving you 7 days' written notice, and will restart once it's paid.
Invoicing each stage
Send an invoice the day a stage is reached, with its own invoice number, like any other invoice. Name the stage, and show the running total so the customer sees where they are: the contract price, what's already been paid, this stage, and what's left after it. A customer who can see the balance going down is a customer who pays the next one.
Using the made-up example above, the stage 2 invoice would read like this.
INVOICE INV-0212. Garage conversion, 14 Oak Avenue. Stage 2 of 4: walls built, window and door fitted. Contract price: £24,000.00. Paid to date (stage 1, INV-0198): £4,800.00. This stage: £7,200.00. Remaining after this stage: £12,000.00. Please pay £7,200.00 by 25 November 2026, reference INV-0212.
What if a stage isn't paid?
Start with a phone call. Most late stage payments are a transfer limit, a remortgage that hasn't landed, or a worry about the work they haven't said out loud. Find out which before you do anything else, and write down what was said.
If it stays unpaid, go back to what you agreed. If your quote said you may pause after written notice, give that notice in writing, with the amount, the invoice number and the date you'll stop. Leave the site safe and weathertight, and keep a record. If your quote said nothing, be careful: walking off a job without a right to can put you in breach of contract, and the customer can claim the cost of someone else finishing it. Talk to them, put the overdue amount in writing, and take advice before you stop.
The unpaid stage is a debt like any other invoice. The usual steps of reminder, final notice and letter before action all apply.
The Construction Act: stage payment rules for business customers
When the customer is a business (a main contractor, a developer, a landlord, a shop), Part II of the Housing Grants, Construction and Regeneration Act 1996, as amended in 2011 and known as the Construction Act, sets payment rules for construction contracts in England, Wales and Scotland. Northern Ireland has its own, similar Construction Contracts (Northern Ireland) Order 1997. The main points:
- A right to stage payments (section 109): you're entitled to instalment, stage or periodic payments, unless the contract says the work will take less than 45 days or you agree it's estimated to.
- Payment notices (section 110A): for each payment, the contract must provide for a notice, given no later than 5 days after the payment due date, saying the sum considered due and how it was worked out. If the payer's notice doesn't come, you can give your own (section 110B).
- Pay the notified sum (section 111): the payer must pay the sum in the notice by the final date for payment, unless they give a pay less notice, in time, saying what they'll pay and why.
- No pay when paid (section 113): a clause saying you'll be paid only when the main contractor is paid is ineffective, except where the party further up is insolvent.
- The right to suspend (section 112): if the notified sum isn't paid by the final date, you can suspend some or all of the work after giving at least 7 days' written notice stating the grounds. The other side must pay your reasonable costs of the suspension, and the time is added to your deadlines.
- Adjudication (section 108): either side can refer a dispute to adjudication at any time, with a decision due within 28 days of referral unless extended.
Where the contract says nothing, and where the Act doesn't reach
If a business contract leaves the payment terms out, the Scheme for Construction Contracts fills the gaps. In England and Wales, a stage payment then falls due 7 days after the end of the period it covers or, if later, when you make your claim; the final date for payment is 17 days after it falls due; and a pay less notice must arrive no later than 7 days before that final date. Scotland has its own Scheme, so check the one that applies.
The Act doesn't apply to a construction contract with a residential occupier: work that's mainly on a house or flat that the customer lives in, or intends to live in. So the extension for a family in their own home is outside it, and the only stage payments, notices and right to stop are the ones in your quote. A landlord doing up a property to let, or a developer, isn't a residential occupier, so the Act applies to them.
Retentions are also in line for change: the Commercial Payments Bill, introduced in May 2026, proposes stopping retentions being withheld under construction contracts. At the time of writing it's not law; check gov.uk for where it's got to.