How to quote a roofing job: the method
Roof prices vary so much from house to house that a single figure tells nobody anything. The method doesn't change, though. Measure, cost the materials with a waste allowance, put days against the work, price the access, and add the lines for what's hidden under the old covering. Then add VAT if you're registered.
- Area: each slope measured, or the flat roof plus its upstands.
- Materials: covering, membrane, battens, fixings, ridge, flashings, insulation if needed, at cost plus your markup.
- Waste allowance on the covering and battens.
- Labour: days for each person, times their day rate.
- Scaffold or access equipment, at the scaffolder's price, for the weeks it's needed.
- Weather allowance, waste removal, and job overheads.
- A provisional rate for rotten timber or anything else found when it's stripped.
How to measure a roof for a quote
For a pitched roof, measure each slope: the length along the eaves times the distance from eaves to ridge up the slope. A measurement from the ground or the floor plan understates the area, because it ignores the pitch. If you can't get up safely on the survey, measure the eaves length from the ground, count courses from photographs or a drone, and say on the quote that the area will be confirmed when the scaffold is up.
For a flat roof, measure the deck and add the upstands, skirtings and any overlap at the edges. Note the outlets, the falls, and whether the deck boards are sound underfoot. Write down the hips, valleys, ridges, abutments, chimneys and roof windows, because each one is time and materials on its own.
Materials and the waste factor
Order quantities are the area plus a waste allowance, rounded up to what the merchant sells. Cuts at hips and valleys, breakages and laps all eat material, so a roof with lots of hips needs a bigger allowance than a plain gable. Ten per cent is a common starting point on a simple roof; use what your own jobs tell you.
Cost every material at what you'll pay, then add one markup you've decided on, not a different one each time. If you're reusing sound slates or tiles, say so on the quote, and say what happens if fewer come off whole than you expected.
Scaffold and access: who arranges it and for how long
Get the scaffolder's price before you quote, for the weeks you need, and ask what each extra week costs. Most re-roofs need scaffold front and back, or edge protection at the eaves; the Work at Height Regulations 2005 require work at height to be properly planned, supervised and carried out by competent people, with the right equipment.
If the scaffold stands on or over the pavement or road, section 169 of the Highways Act 1980 needs a licence from the highway authority, usually the council, before it goes up. Many councils only accept applications from the scaffolding firm, and the fee and notice period vary by council, so check both and build the wait into your start date. Say on the quote who is arranging the scaffold and the licence.
Building regulations on re-roofing: when approval applies
The Planning Portal's guidance for England says you normally won't need building regulations approval to repair or re-cover a roof if less than half the roof is affected and less than a quarter of the building's whole envelope (walls, floor, roof, windows and doors). Go past either and approval is normally needed, which can mean bringing the roof's insulation up to the current standard. Approval is also needed for structural alterations, a covering that performs significantly differently in a fire, or a new covering that increases the weight of the roof covering by 15% or more.
If you're registered with a competent person scheme for roof coverings, you can self-certify instead of applying to building control; the government lists the authorised schemes on gov.uk. Either way, the insulation upgrade is part of the job, so price it in. In Wales the Welsh Government's guidance draws the line lower: repairing or re-covering more than a quarter of the roof area normally means the insulation has to be improved. Scotland and Northern Ireland have their own building standards.
Planning permission is a separate question. Like-for-like re-roofing usually doesn't need it, but a listed building, a conservation area or a flat can be different, so check with the council.
Weather days: price them in and say how they work
A roof can't be stripped in the rain, and a felted flat roof can't be laid on a wet deck. Put a weather allowance into the price as days, from what your own past jobs lost at that time of year, rather than hoping for a dry fortnight.
Then say on the quote what happens to the dates. Customers accept a delay they were told about; they argue with one they weren't. Also say how the roof is kept watertight overnight and over a wet spell while it's open.
What to exclude, and what to make a rate
The exclusions are where a roofing quote protects you. List them in plain words.
- Rotten rafters, battens, fascias and deck boards found when it's stripped: a rate per metre or per board, priced and shown before it's done.
- Chimney rebuilding or repointing, unless it's in the scope.
- Gutters and downpipes, unless they're in the scope.
- Internal decorating, and anything stored in the loft.
- Bats. All bat species and their roosts are protected by law, and gov.uk lists roof repair and replacement as work that can affect them. If there's a sign of bats, the work waits for advice and, if needed, a survey.
- Anything that might be asbestos, such as old cement sheets or flat roof materials: the HSE says asbestos may be in any building built or refurbished before 2000, so it gets checked before it's disturbed.
A worked example price build-up
Here's a re-roof of a small terraced house, both slopes stripped and re-covered in tiles. The rates are made up for the example; use your own. At 80 square metres this is the whole roof, so it needs building control approval or a registered competent roofer, and the insulation upgrade is in the price.
Example only, with made-up rates. Area: two slopes, each 8.0 m along the eaves x 5.0 m eaves to ridge = 40 square metres. Total 80 square metres. Tiles: 80 + 10% waste = 88 square metres at £22.00 = £1,936.00. Membrane, battens and fixings: 88 square metres at £6.00 = £528.00. Ridge tiles and dry ridge kit: £240.00. Lead and flashings: £180.00. Insulation upgrade: £600.00. Materials at cost: £3,484.00. Markup at 10%: £348.40. Materials total: £3,832.40. Labour: two roofers at £240.00 a day, 6 days each = £2,880.00. Weather allowance: 1 day for both = £480.00. Scaffold, front and back, 4 weeks, by the scaffolder including any licence: £1,600.00. Waste removal: £420.00. Overheads for the job (insurance share, scheme registration, van): £200.00. Price: £3,832.40 + £2,880.00 + £480.00 + £1,600.00 + £420.00 + £200.00 = £9,412.40. VAT at 20%: £1,882.48. Total including VAT: £11,294.88. Provisional, only if needed: replacing rotten battens or rafters at a rate per metre, shown to you and agreed before it's done.
How to word it on the quote
The customer agrees to the words, so make them specific. Here's how the example reads to them.
Re-roof at 22 Elm Grove, front and rear slopes. The work: strip the existing tiles and battens and take all waste away. Fit new breathable membrane, battens and tiles, new ridge, and new lead flashings to the chimney. Upgrade the roof insulation to meet building regulations, with the certificate on completion. Scaffold: arranged by us, front and back, for about 4 weeks. Not included: chimney work beyond the flashings, gutters and downpipes, decorating, or clearing the loft. Price: £9,412.40 plus VAT £1,882.48. Total £11,294.88 including VAT. Weather: about 6 working days on the roof, plus allowance for rain. If weather stops work, the finish date moves and the roof is kept watertight. If we find rotten timber when it's stripped, we'll stop, show you, and price the repair before doing it.