How to price a rewire: the method
There's no single fair price for a rewire, because no two houses run their cables the same way. The method is the same every time, though: count what you're installing, put days against it, cost the materials, and add the lines that aren't wiring but still take your time and money.
- Circuits and points: how many of each, room by room.
- Labour: days for each person on the job, times their day rate.
- Materials: cable, boxes, accessories and the consumer unit, at cost plus a markup you've decided on.
- Testing and certification: a day, or part of one, of its own.
- Making good: what you'll do, and what the customer's plasterer or decorator will.
- Waste, overheads for the job, and VAT if you're registered.
What to look at on the survey
Walk every room with the customer and write down what they want where. A rewire is the one chance to put sockets where they're actually used, and the customer will think of more once the boards are up. Agree the layout now, in writing, and price extras as extras.
- Floor construction upstairs and down: suspended timber, concrete, or a mix. Solid floors mean more chasing and more days.
- Loft access and space to run cables, and whether the loft is boarded or full of the owner's things.
- Walls: plaster on brick, plasterboard on studs, or lath and plaster in an older house that cracks when you chase it.
- The existing consumer unit, earthing and bonding, and the meter position.
- Anything that might be asbestos. The HSE says it may be in any home built or refurbished before 2000, including textured ceiling coatings and old floor tiles. If you suspect it, stop and get it checked before you disturb it.
- Who lives there and whether they'll be in during the work.
Counting circuits and points
Write the count down as a schedule, because it's what you'll price from and what the customer will check. List each circuit: lighting circuits per floor, socket circuits, the cooker, an electric shower, the immersion heater, smoke and heat alarms, and any outdoor supply. Then list the points in each room: double sockets, single sockets, light points, switches, fused spurs, data or aerial points if you're doing them.
Time per point varies with the walls and floors, so use your own figures from past jobs. If you don't have them, keep a note of the hours on the next rewire you do; it's the most useful number you'll ever write down.
The consumer unit
A rewire almost always includes a new consumer unit, and replacing a consumer unit is notifiable work in its own right. Price the unit and its protective devices as a line of their own, so the customer can see it. Check the meter tails and the main earth on the survey, and if anything on the supply side looks wrong, raise it with the customer before you price.
Occupied or empty: why it changes the days
An empty house lets you lift every board on a floor at once and work through it. An occupied one doesn't. You'll be moving furniture, laying dust sheets, putting floors back each evening, keeping the fridge and a few lights on, and clearing up at the end of each day so the family can live in it.
Price that time as a line of its own. The right figure is yours, from the hours your own jobs took. Say on the quote what you'll need from the customer: rooms cleared, furniture moved, the loft emptied, and power off for stretches of each day.
Making good: who plasters and who decorates
Chased walls and lifted boards have to be put back, and this is where most rewire disputes start. To you, making good may mean filling the chases ready for a plasterer. To the customer it may mean walls they can paint. Write down exactly what you'll do.
- Floorboards: lifted and refixed, with any that split replaced.
- Chases: filled flush, or patched and left ready for skimming, or plastered by a plasterer you bring in at their price.
- Decorating: almost always excluded. Say so in those words.
- Ceilings: say whether cracks from the work are filled or left for the decorator.
Part P notification and the certificate at the end
In England, the Building Regulations make the installation of a new circuit and the replacement of a consumer unit notifiable, so a full rewire is notifiable. Approved Document P sets out three routes. If you're registered with a competent person scheme, you self-certify, and you or your scheme must, within 30 days of finishing, give the occupier a building regulations compliance certificate and tell building control. If you're not registered, you can appoint a registered third-party certifier before you start, or notify building control before you start, and building control checks the work and issues its own certificate.
Whichever route, the work is inspected and tested to BS 7671, and Approved Document P says a registered installer should give a BS 7671 Electrical Installation Certificate to the person ordering the work. The Welsh Government's guidance gives the same steps for Wales. Scotland and Northern Ireland run their own building standards, so check locally there. Any scheme or building control charge varies, so put it in your overheads at whatever you're charged.
A worked example price build-up
Here's a build-up for a three-bedroom house, occupied, with suspended timber floors. The rates are made up for the example; use your own.
Example only, with made-up rates. Schedule: 9 circuits (2 lighting, 3 sockets, cooker, shower, immersion, smoke and heat alarms). 30 double sockets, 18 light points, 16 switches. Labour: electrician at £260.00 a day and mate at £160.00 a day, 6 days each = £420.00 x 6 = £2,520.00. Occupied house: 1 extra day for both = £420.00. Testing and certification: 1 day, electrician = £260.00. Materials at cost: cable and sundries £780.00, sockets, switches and fittings £420.00, consumer unit and devices £360.00, alarms £150.00 = £1,710.00. Markup at 15%: £256.50. Materials total: £1,966.50. Making good: plasterer, 2 days at £200.00 = £400.00. Waste: £80.00. Overheads for the job (insurance share, scheme and notification, van): £150.00. Price: £2,520.00 + £420.00 + £260.00 + £1,966.50 + £400.00 + £80.00 + £150.00 = £5,796.50. VAT at 20%: £1,159.30. Total including VAT: £6,955.80.
How to present a rewire on the quote
Put the schedule on the quote, so the customer agrees the number of sockets and lights with the price. Then the exclusions, what you need from them, and the certificates they'll get. Extra points they ask for once the boards are up get priced and agreed before you fit them.
Full rewire at 22 Elm Grove, as per the attached schedule of circuits and points. Includes: new consumer unit, all circuits and points on the schedule, smoke and heat alarms, testing, an Electrical Installation Certificate on completion, and building regulations notification through our registered scheme. Making good: floorboards refixed; chases filled and left ready for your plasterer. Decorating not included. We'll need: rooms cleared of small items, the loft accessible, and power off for parts of each day. We'll keep lights and the fridge on overnight. Price: £5,796.50 plus VAT £1,159.30. Total £6,955.80 including VAT. Extra points: priced and agreed in writing before we fit them.